Commission Regulation (EU) 2017/2196 of 24 November 2017 establishing a network c... (32017R2196)
Commission Regulation (EU) 2017/2196 of 24 November 2017 establishing a network c... (32017R2196)
COMMISSION REGULATION (EU) 2017/2196
of 24 November 2017
establishing a network code on electricity emergency and restoration
(Text with EEA relevance)
CHAPTER I
GENERAL PROVISIONS
Article 1
Subject matter
Article 2
Scope
Article 3
Definitions
Article 4
Regulatory aspects
Article 5
Consultation and coordination
Article 6
Regional coordination
Article 7
Public consultation
Article 8
Recovery of costs
Article 9
Confidentiality obligations
Article 10
Agreement with TSOs not bound by this Regulation
CHAPTER II
SYSTEM DEFENCE PLAN
SECTION 1
General provisions
Article 11
Design of the system defence plan
Article 12
Implementation of the system defence plan
Article 13
Activation of the system defence plan
Article 14
Inter-TSO assistance and coordination in emergency state
SECTION 2
Measures of the System Defence Plan
Article 15
Automatic under-frequency control scheme
Article 16
Automatic over-frequency control scheme
Article 17
Automatic scheme against voltage collapse
Article 18
Frequency deviation management procedure
Article 19
Voltage deviation management procedure
Article 20
Power flow management procedure
Article 21
Assistance for active power procedure
Article 22
Manual demand disconnection procedure
CHAPTER III
RESTORATION PLAN
SECTION 1
General provisions
Article 23
Design of the restoration plan
Article 24
Implementation of the restoration plan
Article 25
Activation of the restoration plan
SECTION 2
Re-energisation
Article 26
Re-energisation procedure
Article 27
Activation of the re-energisation procedure
SECTION 3
Frequency management
Article 28
Frequency management procedure
Article 29
Appointment of a frequency leader
Article 30
Frequency management after frequency deviation
Article 31
Frequency management after synchronous area split
SECTION 4
Resynchronisation
Article 32
Resynchronisation procedure
Article 33
Appointment of a resynchronisation leader
Article 34
Resynchronisation strategy
CHAPTER IV
MARKET INTERACTIONS
Article 35
Procedure for suspension of market activities
Article 36
Rules for suspension and restoration of market activities
Article 37
Procedure for restoration of market activities
Article 38
Communication procedure
Article 39
Rules for settlement in case of suspension of market activities
CHAPTER V
INFORMATION EXCHANGE AND COMMUNICATION, TOOLS AND FACILITIES
Article 40
Information exchange
Article 41
Communication systems
Article 42
Tools and facilities
CHAPTER VI
COMPLIANCE AND REVIEW
SECTION 1
Compliance testing of TSO, DSO and SGU capabilities
Article 43
General principles
Article 44
Compliance testing of power generating module capabilities
Article 45
Compliance testing of demand facilities providing demand side response
Article 46
Compliance testing of HVDC capabilities
Article 47
Compliance testing of low frequency demand disconnection relays
Article 48
Testing of communication systems
Article 49
Testing of tools and facilities
SECTION 2
Compliance testing and review of system defence plans and restoration plans
Article 50
Compliance testing and periodic review of the system defence plan
Article 51
Compliance testing and periodic review of the restoration plan
CHAPTER VII
IMPLEMENTATION
Article 52
Monitoring
Article 53
Stakeholder involvement
CHAPTER VIII
FINAL PROVISIONS
Article 54
Amendments to contracts and general terms and conditions
Article 55
Entry into force
ANNEX
|
Parameter |
Values SA Continental Europe |
Values SA Nordic |
Values SA Great Britain |
Values SA Ireland |
Measuring Unit |
|
Demand disconnection starting mandatory level: Frequency |
49 |
48,7 – 48,8 |
48,8 |
48,85 |
Hz |
|
Demand disconnection starting mandatory level: Demand to be disconnected |
5 |
5 |
5 |
6 |
% of the Total Load at national level |
|
Demand disconnection final mandatory level: Frequency |
48 |
48 |
48 |
48,5 |
Hz |
|
Demand disconnection final mandatory level: Cumulative Demand to be disconnected |
45 |
30 |
50 |
60 |
% of the Total Load at national level |
|
Implementation range |
± 7 |
± 10 |
± 10 |
± 7 |
% of the Total Load at national level, for a given Frequency |
|
Minimum number of steps to reach the final mandatory level |
6 |
2 |
4 |
6 |
Number of steps |
|
Maximum Demand disconnection for each step |
10 |
15 |
10 |
12 |
% of the Total Load at national level, for a given step |