COMMISSION DECISION
of 4 July 2006
on State aid which Italy is planning to implement for Cantieri Navali Termoli S.p.A (No C 48/2004 (ex 595/2003))
(notified under document number C(2006) 2972)
(Only the Italian text is authentic)
(Text with EEA relevance)
(2006/948/EC)
Ship |
Cause of delay |
Responsibility |
Problems |
Delay (months) |
Additional months required |
|||||
C.180 |
|
Marnavi (shipowner) |
Suspension of the contract from 1.10.2001 to 30.9.2003 Suspension revoked on 29.9.2003 |
24 |
Not specified |
|||||
|
Marnavi (shipowner) |
Modification of tanks’ size and number, ship length and width |
Not specified |
Not specified |
||||||
|
Force majeure |
Impact of natural disasters on the shipyard, its employees and its subcontractors |
> 2 |
> 2 |
||||||
Total |
More than 26 months |
More than 2 months |
||||||||
Extension requested |
10 months |